GES Chile

Pedro de Valdivia 273
Comuna Providencia
Santiago de Chile
Chileges@services-ges.com

BoP
Installation

782 MW

465 MW

EPC

373 MW

PROJECT GES CHILE

P.E. Talinay
Client: Vestas
Location: 
Ovalle, Chile
Wind turbine: 
15 V100 2MW T80 + 30 V90 2MW T80
Power: 90 MW
Execution tim: June 2012 – December 2012

CHILE | INSTALLATION | BOP WIND|

A record project

Talinay is the first Wind Farm that GES has built in Chile. Construction of 25km of access roads required for the site built in various terrain and ground conditions. The project goal for construction and commisioniong was under tight deadlines for completion. The main milestone was to have all the turbines ready for commissioning before the 31st December 2012.

A comprehensive programme was established to ensure each turbine line with the required production of each phase and the necessary resources to complete all tasks within the required timeframe. We installed a Ready mix Concrete plant on-site for the supply on all turbine foundations, within the wind farm, which resulted in greater flexibility and control. A detailed logistical survey was completed prior to project commencement (to decide between sea or air transport) assisting the procurement and lead in times of required materials in accordance with programme requirements resulting in avoidance of potential delays. Some of the tasks were overlapped such as the concrete paving and the Medium Voltage grid to complete the project within the timeframe. BOP was accomplished within the contractual scope and GES successfully assembled and installed the 45 turbines on time. The project was completed in a record time of 6 months and with no accidents.

Renaico & Los Buenos Aires W.F.
Location: Chile
Power: 112 MW
Execution schedule:November 2015 – November 2016

CHILE | INSTALLATION | BOP WIND |

Cooperating with the local community

Both wind farms were placed in Mapuche territory, native Araucanians. Accesses to the wind farms were complicated. There was a flooding area in Los Buenos Aires, that made the foundations works very hard. Expediting procedures of the customer and some deadlines in the equipment deliveries made the schedule compliance difficult. Three new subcontractors have been hired to work at the substation. More experienced companies were overflow, due to the high demand of the market. Crane movements between platforms needed to be done with partial or total crane dismantling.

GES worked together with the community. Sand and gravel were bought at the local quarry and a Mapuche women cooperative was created for the services at the dining room. It was necessary to build two bridges to access the site. Water was pumped 24 hours a day to make the foundation works possible at the flooding area. Equipment deadlines have been renegotiated with suppliers and air transport was used to shorten deadlines. A very strength coordination was necessary to work with substructure to ensure the quality of the work. Road survey was continuously done, always trying to reduce the number of hours for the crane movements.

Successfully completion of the wind farm without accidents and with satisfactory quality standards.

Sierra Gorda W.F.
Client: ENEL Green Power
Location: 
Calama, Chile
Power
112 MW
Execution time:
June 2016 – December 2016
BOP WIND | CHILE |

Efficient solutions to deal with climatic difficulties

One of the main issues in the project was the "chusca" in this region ground, a fine sand which must be mitigated with water to comliance with the enviromental regulation of the area. Water must be carry on from Calama, the nearest city. Weather conditions made it dificult for the concret to harder. GES was in charge of the construction from the work area facilities for all suppliers working in the plant.

To avoid the chusca inconveniences, the ground was stabilized with quarry material. To compliance the project schedule, GES needed to install two work plants, to have an extra time for the harder of the concret. Electric installation of the working facilities was made with an hybrid system: 3 mini-wind turbines form 1 kW and 44 solar panels from 300 W/ each, with a capacity of 13,5 kW. termal solar power was used for the water. This was the first time an installation alike was installed in a temporary construction.

Despite all the issues and the bad weather conditions during the execution, the project was completed in time applying GES Quality and Health and Safety standards.

Conejo PV. Plant
LocationTaltal, Chile
Power
122 MW
Execution time:
August 2015 – September 2016
 
CHILE | BOP SOLAR | O&M|

One of the biggest PV plants in Chile

The execution of the 122 PV plant was a challenge itself, as it was the biggest solar plant constructed until that moment by GES. PV plant was located in a remote area in the Atacama desert, which made the logistic very difficult. Equipment was delivered from very different places in the world (China, Spain, Sweden, Mexico... ) The project included two substations and an interconnection line.

More than 600 technicians were working at the plant at the same time in some stages of the project. More than 1.000 containers were delivered to plant. 1.26 Million photovoltaic modules were installed.

The project was completed following GES quality standards. This proves GES potential to construct utility scale projects.

Negrete W.F.
ClientMainstream
LocationLos Ángeles, Chile
Wind turbineGoldwind 1500 KW Wind Turbine Generator System
Power33 MW
Execution timeDecember 2012 – December 2013
BOP EÓLICA CHILE BOP WIND |

Minimizing the local impact through cooperation with the community

It was a big project which includes: permits processing, geotechnical investigation, civil works, substation and control building, engineering, power line, assembly and commissioning. The deadline was very tight due to a delay on hte the foundations design. Winter weather conditions complicated the usual rhythm of civil works. The wind farm is located in the middle of a community of farmers and cattle breeders

An increase of resources has been implemented in order to reach the deadline, which was extended due the delay of the final design of foundations. H&S measurements following GES standards were applied, to reach a safe work site and to prevent any interference to the local population. GES collaborated to maintain a friendly relation with the land owners and the community, helping them with the tools and resources on site and trying to minimize the impact of the project. Continuous interface between GES staff on site, GES engineering department in Spain and the Client in Chile and in Ireland.

The result in terms of quality and schedule compliance was excellent. Continuous improvement in H&S issues along the Project, reflected in the good results obtained in the audits done by the Client. All fo this helped to increase of GES notoriety in Chile, a growing market at that time.

1.     Información legal

1.1.  En cumplimiento del artículo 10 de la Ley 34/2002, de 11 de julio, de servicios de la sociedad de la información y de comercio electrónico (LSSICE) presentamos la siguiente información:

Razón Social: GLOBAL ENERGY SERVICES SIEMSA SA (GES)

Dirección: Parque Tecnológico Bizkaia Edificio 407-48170 Zamudio– Vizcaya (España).

C.I.F.: A82509779

Teléfono: (+34) 944 712 131

E-mail: ges@services-ges.com

Datos de la inscripción en el Registro Mercantil Vizcaya Folio: 142  Tomo: 5471

2.     Protección de datos

2.1.  Completando el formulario de registro o de contacto, enviando un correo electrónico, o llamando por teléfono, sus datos personales pasarán a ser responsabilidad de la empresa cuyos datos se relacionan en el apartado 1. Información Legal.

Además, el usuario es informado de que sus datos profesionales y de contacto serán proporcionados para su tratamiento, a otras entidades pertenecientes al Grupo de GES y a sociedades participadas por cualquiera de las sociedades que conforman el Grupo de GES.

2.2.  Estos datos se utilizan para responder a su solicitud o consulta a la mayor brevedad posible y para comunicarnos comercialmente, porque usted nos los proporciona informada y libremente con esas finalidades.

Si usted nos proporciona un currículum sus datos se utilizarán para incorporarlo a presentes y futuros procesos selectivos en nuestra empresa y para comunicarnos con usted incluso por medios electrónicos en relación con su candidatura.

Para otros tratamientos o finalidades relacionados con la prestación de nuestros servicios o el desarrollo de nuestra actividad, usted puede solicitar más información en nuestra dirección de contacto.

2.3.  Los datos personales recogidos en nuestra página web son tratados cumpliendo con las exigencias del Reglamento (UE) 2016/679 del Parlamento Europeo y del Consejo, de 27 de abril de 2016, relativo a la protección de las personas físicas en lo que respecta al tratamiento de datos personales y a la libre circulación de estos datos.

2.4.  Así mismo, garantizamos que los datos personales son tratados de manera lícita, leal y transparente, y son recogidos con fines determinados, explícitos y legítimos, manteniéndose limitados a dichos fines y actualizados si fuera necesario. No se permitirá la identificación de los interesados durante más tiempo del necesario y se garantizará su seguridad mediante las medidas técnicas y organizativas adecuadas.

2.5.  Una vez los datos no sean necesarios para los fines con los que fueron recogidos,  se conservarán a disposición de las administraciones públicas competentes durante los plazos legales de conservación, es decir mientras una ley nos pueda exigir que los presentemos. Expirados estos plazos serán suprimidos.

2.6.  Puede ejercer los derechos de acceso, rectificación, supresión, oposición así como los demás derechos que le otorga la normativa de protección de datos sobre los datos de carácter personal presentando una copia de un documento identificativo en GES – Parque Tecnológico Bizkaia Edificio 407 – 48170 Zamudio – Vizcaya (España).

2.7.  Puede encontrar más información sobre sus derechos o presentar una reclamación ante la autoridad de control competente en la Agencia Española de Protección de Datos http://www.agpd.es – C/ Jorge Juan, 6. 28001 – Madrid (901 100 099 – 912 663 517).

3.     Limitación de Responsabilidades

3.1.  GES proporciona el sitio web corporativo como medio de dar a conocer sus productos y servicios, y permitir el contacto con los clientes. La información de la página web se presenta de modo meramente orientativo o divulgativo y en ningún momento será considerada vinculante. Para la contratación de los productos o servicios de la entidad se estará a lo dispuesto en presupuestos y contratos debidamente formalizados.

3.2.  La entidad no se responsabiliza sobre los posibles daños informáticos que pueda sufrir el usuario mientras visita nuestra página web entendiendo que aquellos no puedan ser imputables a la entidad.

3.3.  La entidad tampoco se responsabiliza del contenido de los sitios gestionados por terceros que se enlacen desde la página web, así mismo dichos enlaces no implicarán la existencia de algún tipo de relación por parte de GES con esos terceros.

4.     Propiedad Intelectual

4.1.  Todos los contenidos de esta página web entendiendo como tales los textos, dibujos, gráficos, fotografías, imágenes, vídeos, música, código, el propio diseño de la misma y cualquier otra creación son propiedad de GES o de sus respectivos titulares mediante la correspondiente licencia, autorización o cesión sobre los derechos y están protegidos en función de la legislación sobre la Propiedad Intelectual e Industrial.

4.2.  En ningún caso se entenderá que la puesta a disposición del público de la página web constituye renuncia, cesión o licencia de los derechos que GES tiene sobre los contenidos de la misma.

4.3.  Queda prohibido cualquier uso de los contenidos de nuestra página web incluida la modificación, copia, reproducción, transmisión, etcétera sin la previa autorización por escrito de la entidad.